Our Clients

O U R  C L I E N T S

 

Completed Projects

 

Consultancy Services provided to M/s L&T

 

We have provided consultancy services for following four SPV projects of 17 MM, EPC Work done by M/s L&T: -

 

1.   M/s D.J. Malpani – 13 MW

2.   M/s Lahoti Overseas Pvt. Ltd. – 2 MW

3.   M/s Charter Gold Financial Services Pvt. Ltd. – 1 MW

4.   M/s Dindyal Commodities Pvt. Ltd. – 1 MW

 

Consultancy Services provided from 22.12.2012 to 26.03.2013: -

 

1.  Approval for combine Power Evacuation Plan.

2.  Arranging  “In-Principle”  Clearance  of Projects  under REC  Scheme as  per relevant

clause of Rajasthan Solar Energy Policy, 2011.

3.  Arranging of conversion of agriculture land to Industrial land separately for each of 4 projects.

4.  Arranging  Approval  of  Project  (under  REC  Scheme)  from  State  Level  Empowered

Committee (SLEC).

5.  Singing of PPA with DISCOMs.

6.  Approval of connectivity from RVPN for connecting transmission line and plant to

RVPN Substation.

7.  Arranging of Bay for Transmission Line.

8.  Metering arrangement and approval of metering scheme from RVPN / DISCOM.

9.  Co-ordination for Construction of Bay and arranging of equipments for 33 kV Bay.

10. Assisting in Filling of application for registration of project under REC. Accreditation of project under REC from RREC.

11. Arranging Govt. Approval under section 68 for Transmission Line.

12. Arranging Approval of connectivity from SE (NPP) RVPN for connecting transmission line and plant to RVPN Substation when Bay and power plant is ready before arranging Connectivity Team.

13. Arranging Documents Customs and Excise duty Exemption Recommendation from

RREC:

14. Arranging approval of drawings for each solar from Chief Electrical Inspector.

15. Arranging    Clearance    from    Chief    Electrical    Inspector    for    readiness    before commissioning.

16. Arranging final Clearance from Chief Electrical Inspector for commissioning   of plant for each project.

17. Arranging for Creation of Committee by RDPPC for Connectivity  of Solar power plant.

18. Arranging for Creation of Committee by RDPPC for Commissioning    of Solar power plant.

19. Arranging approval of Consent to Established and Consent to operate from RPCB.

All 17 MW projects are commissioned. Started works on 22nd Dec. 2012 and project were commissioned on 26th March 2013.

 Consultancy Services provided to M/s Rays Power Expert Pvt. Ltd.

 

We have provided consultancy services to assistance in approval of Combine Power evacuation Plan, approval of Connectivity with RVPN Grid, Singing of PPA with DISCOMs, arranging of Bay for transmission Line etc. for following projects executed / under execution by Rays Power Expert Pvt. Ltd. in Rays Solar Park.

 

1.   M/s R. H. Prasad and Company Pvt. Ltd.

2.   M/s Nishka Power Project Company Ltd.

 

3.   M/s Hasya Enterprises Pvt. Ltd.

4.   M/s Impact Solar Power Pvt. Ltd.

5.   M/s Raj Overseas.

6.   M/s Kishan Gopal Rungta (P) Ltd.

7.   M/s Realstep Infrastructure (P) Ltd.

8.   M/s Navkar Woollens (P) Ltd.

9.   M/s KC India Limited.

10. M/s Shri Giriraj Energy Pvt. Ltd.

11. M/s Realstep Infrastructure (P) Ltd.

12. M/s Impact Solar Power Pvt. Ltd.

13. M/s Shri Giriraj Energy Pvt. Ltd.

14. M/s Hasya Enterprises Pvt. Ltd.

15. M/S. Pragat Akshay Urja Pvt. Ltd.

16. M/S Bikaji Foods International. Ltd.

17. M/S N K Gold Medallion Pvt. Ltd.

18. M/S Jai Mangal Infrapower Pvt. Ltd.

19. M/s Aman.

20. M/s Vinay.

M/s GSF Capital PTE Ltd., 3801, K. Wah Centre, 1010, Huai Hai Road, Shanghai – 50 MW

 

Technical Consultancy for: -

1. Land indemnification and selection of Govt. Land.

2. Registration of project in RRECL, Power evacuation, In Principle clearance, SLEC

approval and PPA etc.

3. Various clearances required for solar power project from various agencies in

Rajasthan / India.

M/s GreenOLite (India) technologies Pvt. Ltd. – 30 MW Technical Consultancy for: -

1.  Power evacuation approval from RRVPNL.

2.  In Principle clearance from RREC for proposed project under clause 5.1.6 of

Rajasthan Solar Energy Policy 2011.

Projects Under Implementation

 

M/s Laxmi Diamond Private Limited – 20 MW

 

Consultancy services to M/s Laxmi Diamond Private limited for: -

 

1.  Registration of project with RREC. – Completed

2.  Approval for Power Evacuation Plan. – Completed

3.  Arranging  “In-Principle”  Clearance  of  Projects  under  REC  Scheme  as  per

relevant clause of Rajasthan Solar Energy Policy, 2011.

4.  Arranging   Approval   of   Project   (under   REC   Scheme)   from   State   Level

Empowered Committee (SLEC).

5.  Singing of PPA with DISCOMs.

6.  Approval of connectivity from RVPN for connecting transmission line and plant to RVPN Substation.

7.  Arranging of Bay for Transmission Line.

8.  Metering arrangement and approval of metering scheme from RVPN / DISCOM.

9.  Co-ordination for Construction of Bay and arranging of equipments for 33 kV Bay.

10. Assisting  in  Filling  of  application  for  registration  of  project  under  REC.

Accreditation of project under REC from RREC.

11. Arranging Govt.  Approval under section 68 for Transmission Line.

12. Arranging Approval of connectivity from STU.

13. Preparing     Documents     for      Customs     and      Excise      duty     Exemption

Recommendation from RREC and MNRE.

14. Arranging approval of drawings for each solar from Chief Electrical Inspector.

 

15. Arranging  Clearance  from  Chief  Electrical  Inspector  for  readiness  before commissioning.

16. Arranging final Clearance from Chief Electrical Inspector for commissioning.

17. Arranging for Creation of Committee by RDPPC for Connectivity       of Solar power plant.

18. Arranging for Creation of Committee by RDPPC for Commissioning    of Solar power plant.

19. Arranging approval of Consent to Established and Consent to operate from

RPCB.

Navkar Solar Park – 20 MW at Bikaner, Rajasthan

 

We are working as consultant cum Technical support agency for developing 20 MW Navkar Solar Park and 33 kV Transmission Line for evacuation of generated power.

20 Nos. of solar plants each having 1 MW capacity will be developed in this Solar

Park.

 

Scope of Services: -

1.  Arranging SLSC approval of 1st 1MW solar plant. (Work already completed)

 

2.  SLEC approval of 1st 1 MW project

3.  Arranging combine power evacuation approvals for 20 MW solar park.(work already completed)

4.  Arranging  Registration  of  balance  18  Nos  of  each  1  MW  solar  projects  of

Investors with RREC time to time and Arranging SLSC approval and SLEC

approval.

5.  Overall Planning of 20 Nos of each 1 MW Solar Plants and pooling station.

6.  Arranging of all approvals for setting up of 1 MW solar projects from RREC, Discom etc.

7.  Guidance in Design, Engineering, for setting up of each 1 MW solar plant.

8.  Preparation  of  Bid  Documents  for  modules,  Inverters,  cost  evaluations, ordering of materials for all the 20 Nos. 1 MW power plant and there purchase.

9.  Preparation of Technical specification of balance equipment and materials of

solar plant and there purchase.

10. Preparation of Bid Documents, Bids Evaluations, Selection of Sub contractors for erection, civil work and AC, DC electrical works.

11. Arranging PPA with Discoms under REC.

12. Other works as detailed in MOU.

  Devesh Solar Energy Private Limited – 1 MW

 

Scope of services of CVK Solar Enterprises: -

 

1.  Formation of Company.

 

2.  Registration of project with RREC

3.  Preparation of tender document and other formalities.

4.  Submission of e-tender documents to RREC.

5.  Negotiation of tariff with RREC.

6.  Arranging allotment of project from RREC.

7.  Arranging power evacuation approval.

8.  Arranging SLSC approval and SLEC approvals.

9.  Arranging of all approvals for setting up of 1 MW solar projects from RREC, Discom, Pollution control board, Electrical Inspector etc.

10. Design, Engineering and procurement work for setting up solar plant and doing

EPC.

11. Preparation of Technical specification of Equipment and Materials of solar plant

12. Preparation of Bid Documents, Bids Evaluations, Selection of Sub contractors for erection, civil work and AC, DC electrical works.

 

13. Arranging PPA with Discoms under REC.

14. Other works as detailed in MOU.

15. Online registration for project for taking Excise duty and Custom duty benefit and finalisation of Bill of material.

16. Preparation of drawings of civil works, structures, Current ratings and selection of cables.

17. Supervision of all civil work and Electrical works.

18. Approval of Bay and arranging connectivity approval.

19. Arranging commissioning of project.

20. O&M of project after commissioning.

21. Arranging payments of Bills of energy export.

 

Mayank Solar Energy Private Limited – 1 MW

 

Responsibilities of CVK Solar Enterprises: -

 

1.    Formation of Company.

 

2.    Registration of project with RREC

3.    Preparation of tender document and other formalities.

4.    Submission of e-tender documents to RREC.

5.    Negotiation of tariff with RREC.

6.    Arranging allotment of project from RREC.

7.    Arranging power evacuation approval.

8.    Arranging SLSC approval and SLEC approvals.

9.    Arranging of all approvals for setting up of 1 MW solar projects from RREC, Discom, Pollution control board, Electrical Inspector etc.

10.   Design, Engineering and procurement work for setting up solar plant and doing EPC.

11.  Preparation of Technical specification of Equipment and Materials of solar plant

12.  Preparation   of   Bid   Documents,   Bids    Evaluations,    Selection   of    Sub contractors for erection, civil work and AC, DC electrical works.

13.  Arranging PPA with Discoms under REC.

14.  Other works as detailed in MOU.

15.  Online  registration  for  project  for  taking  Excise  duty  and  Custom  duty benefit and finalisation of Bill of material.

16.  Preparation  of  drawings  of  civil  works,  structures,  Current  ratings  and selection of cables.

17.   Supervision of all civil work and Electrical works.

18.  Approval of Bay and arranging connectivity approval.

19.  Arranging commissioning of project.

20.  O&M of project after commissioning.

21.  Arranging payments of Bills of energy export.

 

 

Inspira Power India Private Limited – 50 MW – Under Open Access

ISLA Energy Private limited – 50 MW – Under Open Access

Arion Energy Private Limited – 50 MW – Under Open Access

 

Consultancy services for location of solar plant and Power Evacuation

Approval.